ANALISIS KAPASITAS PRODUKSI PADA LINI PRODUKSI BARU FORD P702 HVPO DENGAN PENDEKATAN METODE ROUGH CUT CAPACITY PLANNING (STUDI KASUS DI PT CSB)
Abstract
ABSTRACT
This research is to analyze capacity requirements and availability on the production line. This research in PT CSB project FORD P702 HVPO production line. Data analysis used the Rough Cut Capacity Planning (RCCP) method by measuring work (time study), forecasting, aggregate planning, master production schedule and capacity analysis with RCCP.
Based on research, standard time is 745 seconds / unit for new prodject FORD P702 HVPO. The best forecasting method is use Single Moving Average with an MAD error value of 0.04 and MSE error value of 0.021. Aggregate planning calculation results is 27144 units per year with cost of Rp 49,563,348 per year. And the conclusion is the capacity of the FORD P702 HVPO production line is sufficient and feasible to meet customer needs. This research is calculated based on the total production capacity of 19,958,400 seconds per unit in 1 year and the total required capacity of 18,618,775 seconds per unit in 1 year.
Keywords
Full Text:
PDFReferences
Cahyawati, A. N., & Prastuti, N. D. (2018). Analisis Pengukuran Waktu Kerja Pada Proses Packaging Kasa Hidrofil Menggunakan Metode Stopwatch Time Study. 256–260.
Faisal, M. (2018). Perang Dagang AS VS China: Bagaimana Dengan Indonesia? In Uraian Diskusi Keadilan Ekonomi IGJ.
Jurnal Teknik Industri USU, 2(1), 15–23.
Ishak, A. (2019). Manajemen Operasi (2nd ed.). Retrieved from http://usupress.usu.ac.id
Kesavan, R., Elanchezhian, C., & Ramnath, B. V. (2009). Proses Planing and Cost Estimation (2nd ed.). New Age International (P) Ltd.,Publishers.
Matswaya, A., Sunarko, B., Widuri, R., & Indriati, S. (2019). Analisis Perencanaan Kapasitas Produksi Dengan Metode Rought Cut Capacity Planning (RCCP) Pada Pembuatan Produk Kasur Busa (Studi Pada Pt Buana Spring Foam di Purwokerto). Performance, 26(2), 128.
Pujiatmo, S. (2013). Studi Deskriptif Pengelolaan Dan Pengembangan Usaha Pada Kecap Tiga Udang Di Madura. Agora, 1(1).
Rachman, T. (2016). Penggunaan Metode Work Sampling untuk Menghitung Waktu Baku dan Kapasitas Produksi Karungan Soap Chip di PT. SA. Jurnal Inovasi, 9(1), 48–60.
Rinawati, D. I., Sari, D. P., & Muljadi, F. (2013). Penentuan Waktu Standar Dan Jumlah Tenaga Kerja Optimal Pada Produksi Batik Cap (Studi Kasus: Ikm Batik Saud Effendy, Laweyan). JaTi Undip : Jurnal Teknik Industri, 7(3), 143–150. https://doi.org/10.12777/jati.7.3.143-150
Rusdiana, (2014). Manajemen operasi. Retrieved from http://digilib.uinsgd.ac.id/8788/1/Buku Manajemen Operasi.pdf
Setiabudi, Y., Afma, V. M., & Irwan, H. (2018). Perencanaan Kapasitas Produksi ATV12 Dengan Menggunakan Metode Rough Cut Capacity Planning (RCCP) Untuk Mengetahui Titik Optimasi Produksi (Studi Kasus di PT Schneider Electric Manufacturing Batam ). Jurnal Profisiensi, 6(2), 80–87.
DOI: https://doi.org/10.33373/profis.v9i2.3674
Refbacks
- There are currently no refbacks.
Copyright (c) 2021 Universitas Riau Kepulauan
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
E-ISSN 2598-9987
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
PROFISIENSI: Jurnal Program Studi Teknik Industri
Building A, 1st Floor, Faculty of Engineering, University of Riau Kepulauan
Jl. Pahlawan No.99, Batu Aji, Batam, Kepulauan Riau
Email: Profisiensi@journal.unrika.ac.id